Our Projects
Location: Waikato
Client: Dempsey Wood
Scope: Drainage ( Wastewater and Stormwater, triton, and Soak pits systems)Wing wall.
Outcome: All our resources are on site and ready to go – the project has recently commenced.

01
Summerset Extension
02
Summerset Cambridge
Location: Waikato
Client: Dempsey Wood
Scope: Drainage (installation of Wastewater and Stormwater), backfill compaction, soak pit and Triton system installation, earthworks (Construction of twin pipe wing wall with gabion mattress), 1800mm erosion storage tanks, and deep excavation, Wing wall.
Outcome: The drainage works were completed on schedule, and quality workmanship was provided. All camering of lines and site inspections passed.

.jpg)
03
Lockerbie SP4
Location: Waikato
Client: Dempsey Wood
Scope: 2.4mm/6m deep - Pump station installation – Stormwater and wastewater installation, wingwall.
Outcome: The project was completed within the stipulated timeframe, with high workmanship and attention to detail standards. All camering of lines and site inspections passed.
04
Filtec
Location: Waikato
Client: Dempsey Wood
Scope: Specialized installation of wastewater and stormwater systems for the Filtec treatment plant.
Outcome: The project was completed on time, meticulously adhering to environmental regulations and client specifications. Our team’s expertise in handling complex drainage systems was instrumental in the project’s success.

_edited_edited.jpg)
05
Kopu Hikua
Location: Waikato
Client: Fulton & Hogan
Scope: Deep excavation, 1800mm pipe installation, compaction, loading and removal, boulder removal, rip wrap and sandbagging, placement, and finishing, Culverts.
Outcome: The project was completed on time and within budget. The deep excavation and installation of large-diameter pipes required precision and expertise, which was successfully delivered, ensuring high-quality results.
06
Pikowai
Location: Waikato
Client: Dempsey Wood
Scope: Drainage ( Wastewater and Stormwater installation. Rain gardens. Deep excavation in complex ground condition. Wing wall.
Outcome: We have completed our wastewater, and we are 1 month ahead of schedule for wastewater and currently 1 month away from finishing our stormwater, which will put us 2 months ahead of schedule.
.jpg)

07
Akakura